一,廊坊裝配流水線:三流道倍速鏈操作說明:
廊坊裝配流水線 ,廊坊倍速鏈流水線 ,廊坊倍速鏈裝配生產(chǎn)線:三流道倍速鏈采用增速鏈或滾子鏈為輸送介質(zhì),導軌采用較為先進的鋁合金型材(912鋁型型材),由主機帶動輸送鏈條,再托拖動工裝板運行,當線體作自由節(jié)拍運行時,工裝板由輸送鏈條托拖到達每工位工作位置,再由腳踏開關(guān)拉制氣動阻擋器,使工裝板停在預定工作位置,旋轉(zhuǎn)工裝板可作360度或180度旋轉(zhuǎn)。完成工序后,操作人員只要踏腳踏開關(guān),工裝板即可進入下一道工序。
廊坊裝配流水線:三流道倍速鏈工裝板到達終端時,觸動終端行程開關(guān),能自動橫向移動至對邊,繼行未完的工序,實現(xiàn)工裝板在環(huán)形軌道內(nèi)自動往復循環(huán),三流道中間道作為空板返回,采用歐姆龍CPM1A可編程序控制器控制。
二,廊坊裝配流水線:三流道倍速鏈開機操作
(1) 打開廊坊倍速鏈裝配生產(chǎn)線:三流道倍速鏈總開關(guān);
(2) 按控制箱操作面板上的“馬達”——“啟動”;“照明”—“啟動”等。
三, 廊坊裝配流水線:三流道倍速鏈關(guān)機操作
關(guān)閉“馬達”,調(diào)速器調(diào)至“0”,關(guān)閉“照明”等。
關(guān)閉總開關(guān)。
1. Assembly line: Operation instructions for three-runner double-speed chain:
Assembly line, double-speed chain assembly line, double-speed chain assembly production line: three-channel double-speed chain adopts speed-increasing chain or roller chain as the conveying medium, and the guide rail adopts more advanced aluminum alloy profiles (912 aluminum profiles), and the conveyor chain is driven by the host. The tooling board is dragged to run. When the line body is running in free rhythm, the tooling board is dragged by the conveyor chain to the working position of each station, and then the pneumatic stopper is pulled by the foot switch to stop the tooling board at the predetermined working position. The rotating tooling board can be rotated 360 degrees or 180 degrees. After the process is completed, the operator only needs to step on the foot switch and the tooling board can enter the next process.
Assembly line: When the three-channel double-speed chain tooling plate reaches the terminal, it can touch the terminal stroke switch, and it can automatically move laterally to the opposite side, continue the unfinished process, and realize the automatic reciprocating cycle of the tooling plate in the circular track, and the three-channel middle channel is used as an empty plate Return, using Omron CPM1A programmable controller to control.
2. Assembly line: start-up operation of three-runner double-speed chain
(1) Turn on the double-speed chain assembly line: the main switch of the three-runner double-speed chain;
(2) Press "Motor"-"Start"; "Illumination"-"Start" on the operation panel of the control box.
3. Assembly line: shutdown operation of three-channel double-speed chain
Turn off the "motor", adjust the governor to "0", turn off the "lighting" and so on.
Turn off the main switch.